Chat with us

Inspirational journeys

Follow the stories of academics and their research expeditions

Critical Path Method In Project Manangment.

Mudessar Afraz

Fri, 26 Apr 2024

The Critical Path Method (CPM) is a widely used technique in construction project management for scheduling and coordinating tasks. It is a step-by-step process that helps project managers identify the critical path of a project, which is the sequence of tasks that must be completed on time for the project to be completed on schedule.

Here's an example of how the CPM method could be applied to a construction project:

Identify all tasks required to complete the project. For example, tasks might include site preparation, excavation, foundation work, framing, electrical, plumbing, and finishes.

Create a flowchart or network diagram that represents the interdependencies between tasks. For example, framing cannot begin until the foundation work is completed.

Estimate the duration of each task. For example, site preparation might take 2 weeks, excavation might take 3 weeks, and framing might take 4 weeks.

Identify the earliest possible start and finish dates for each task based on its dependencies. For example, the earliest possible start date for framing is 2 weeks after the start of site preparation and 3 weeks after the start of excavation.

Identify the latest possible start and finish dates for each task based on the project completion date. For example, the latest possible finish date for framing is 1 week before the project completion date.

Determine the critical path by identifying the tasks that have no slack or float time. The critical path is the sequence of tasks that must be completed on time for the project to be completed on schedule.

Continuously monitor and update the schedule as the project progresses to ensure that the critical path is being followed and that the project is on schedule.

Any delay in critical path activities will cause a delay in the project completion and need to be addressed as soon as possible.

By following these steps, project managers can use the CPM method to effectively schedule and coordinate tasks in a construction project, ensuring that the project is completed on time and within budget.



0 Comments

Leave a comment